More Tree Cutting on Hodnet Bypass

Tree Cutting on A53 - Feb/Mar 2018

We recently gave advance notice of tree cutting work on the A53. Now roadworks.org is warning of 4 more weeks of similar maintenance work.
The next phase can be found listed here, but if the date range is extended to ‘Next 3 Months’ then all the phases are listed.
Details for each location are listed below, click on the map for larger image.

Tree Cutting on A53 - Feb/Mar 2018A: 26 Feb – 3 Mar
Location: A53 Heathbrook Junction To Lostford Junction
Traffic lights, etc: Traffic control (two-way signals)
Description: Tree cutting works
Works ref: UJ015282014531
B: 5 Mar – 9 Mar
Location: A53 Heathbrook Junction To Lostford Junction
Traffic lights, etc: Traffic control (two-way signals)
Description: Tree cutting works
Works ref: UJ015282014532
C: 12 Mar – 16 Mar
Location: A53 Heathbrook Junction To Lostford Junction
Traffic lights, etc: Traffic control (two-way signals)
Description: Tree cutting works
Works ref: UJ015282014533
D: 19 Mar – 20 Mar
Location: A53 Espley Roundabout To Stoke On Tern Junction
Traffic lights, etc: Traffic control (two-way signals)
Description: Tree cutting works.
Works ref: UJ01528201451
E: 21 Mar – 22 Mar
Location: A53 Espley Roundabout To Stoke On Tern Junction
Traffic lights, etc: Traffic control (two-way signals)
Description: Tree cutting works.
Works ref: UJ015282014514