More Roadworks on A53!

Roadworks Sign

Roadworks SignJust when one thought it would be safe to use the A53 again after the completion of the resurfacing of Espley Roundabout, more works have been announced.
Roaworks.org carries a notice of work on the A53 near Hopton from Thursday 23 Nov 2017 for a week. The notice states:

A53 From Hopton Church Junction to Espley Roundabout, Hodnet, Shropshire
23 November — 30 November
Delays likely Traffic control (two-way signals)
Works location: A53 From Old Church to Jcn by layby Hodnet Shropshire TF9 3LE
Works description: Rolling 2 way traffic lights required to access boxes in carriageway. To allow BT cablers to complete underground cabling for BDUK work, required for 10 days 09:30-15:30 as per Plant Survey 255-s001636.
Please could we have lights on site for 7 days (with weekend working).
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC005CR18WIBPKP3HK061117