Wollerton Water Main Replacement – Update: 23 November 2018

Wollerton Road Closure Map Oct 2018 to March 2019

For full information about 22 Weeks of Roadworks in Wollerton please see the main story.
Update: 23 Nov. 2018
The following update has been sent to the webteam by Samantha Pedley, Amey Customer Liaison Officer. Amey are the contractors carrying out the work for Severn Trent Water.

Mill Rd, Wollerton
Samantha Pedley, Amey Customer Liaison OfficerThings are progressing on schedule with another 260mm of watermain being installed this week which should take us to the edge of the village.
Further works are required in Wollerton for connections to be done and renewing or transferring your water services on to the new main.
Please be mindful when driving through our works, our workforce may be in the road, so please pass slowly. It is important to be aware if you damage your car, you may not be covered by your insurance as you are within a road closure.
Thank you for your patience and understanding during these works.

Last weekend some local residents had concerns about road plates covering a hole on the old railway bridge moving apart due to traffic driving over them. The site agent says that this problem was addressed on Wednesday this week.
In you have concerns about this or any other matter in connection with the ongoing work you can contact Samantha direct on 07725-073188 or get in touch with the webteam.