Wollerton Water Main Replacement – Update: 15 December 2018
For full information about 22 Weeks of Roadworks in Wollerton please see the main story.
Update: 15 Dec. 2018
The following update has been sent to the webteam by Samantha Pedley, Amey Customer Liaison Officer. Amey are the contractors carrying out the work for Severn Trent Water.
Mill Rd, Wollerton
All the pipework has been installed,there are a small number of connections still to complete.
The barriers will remain in place over the weekend but next week reinstatement work should be completed. The site should be clear in the village by the end of that week. The expectation is, all being well, we will be finished in the village in time for Christmas (ahead of schedule).
Work on the main road toward Lostford, will start in the new year.